After almost a year of structural repairs, the US 60/62 Mississippi River bridge at Birds Point reopened to traffic on Wednesday.
The $5.86 million project began in October of 2023, and was anticipated to be completed Oct. 1, but the work was finished a week ahead of schedule.
After inspections in the spring of 2023, crews repaired more than 100 joints on the 94-year-old bridge while trucks and motorists from Kentucky were detoured through Cairo to I-57.
Meanwhile, the final design stage is under way for construction of a replacement for the nearby 88-year-old US 51 Ohio River bridge from Wickliffe to Cairo. Construction is not anticipated to begin before 2028.
Advertisement
After a year of repairs, US 60/62 Mississippi River bridge has reopened
Advertisement
Latest Local & Regional
Local & Regional
an hour ago
Local & Regional
11 hours ago
Local & Regional
17 hours ago
Local & Regional
yesterday
Local & Regional
yesterday
ADVERTISEMENT
Most Read >
ADVERTISEMENT
Latest Local & Regional
Local & Regional
an hour ago
Local & Regional
11 hours ago
Local & Regional
17 hours ago
Local & Regional
yesterday
Local & Regional
yesterday
Advertisement
ADVERTISEMENT